AGM - Managing Director's Presentation
Released
Released
Announcement PDF
Building Australia’s only
pure-play silver mine
November 2026
Lachlan Wallace, Managing Director
2
Investigator Silver
Rare combination of commodity momentum, a project and team to deliver it, at a compelling valuation
Why Silver? Why Investigator? Why Now?
• Five years of market deficits
• Growing industrial demand
• Inelastic supply response
• Simple project, strong economics
• Tier 1 mining jurisdiction
• Proven South Australian mine
builders
• Significant exploration upside
• Fully funded to FID
• Trading at significant discount
to global peers
• 30,000m drilling program
underway
57Moz
Resource
A$ 618M
Pre-tax NPV8
A$ 50M
Enterprise Value
A$ 55M
Cash
(30 Sep 2026)
3
Silver Market Balance (Moz)
Source: Silver Institute
Gold, 15.5%
Copper,
26.8%
Lead/Zinc, 29.4%
Primary
Silver,
27.8%
Other,
0.5%
Source: World Silver Survey 2026
Consistent market deficits year on year… … With limited ability for supply to respond
Silver Thematic
Growing silver demand persistent deficits and constrained supply
4
South Australia (Gawler Craton)
Located in the right jurisdiction and postcode
Australia’s #1 mining jurisdiction
Located in the Gawler Craton
Close to regional mining hubs
Multiple operating mines nearby
5
Paris Location
Straight forward permitting
No competing land use
Flat, dry, highly saline groundwater
Designed with Traditional Owners
Heritage surveys complete over
entire project footprint
6
Simple Mining – Low Technical Risk
Shallow, simple open pit
Flat orebody – 600m wide x 2,000m long
Low strip ratio – ore starts <10m below surface
Simple pit – only 175m deep
Stage 1 North
Stage 1 South
Stage 2 North
Ultimate Pit
7
Conventional Processing
Proven technology with a standard silver flow sheet
Off the shelf equipment
Producing silver doré
Simple logistics
8
ASX announcement 27 February 2026 Paris DFS Confirms Maiden Ore Reserve, Strong Economics
Outcomes are pre-tax,ungeared on a 100% project basis.Assumptions: spot pricing assumes a silver price of US$60/oz; AUD:USD 0.69; 8% discount rate; no escalation.Margin = EBITDA/Revenue.
Inferred Mineral Resourcesaccount for 14% of the production target and carry low geological confidence. Further drilling may not supportconversion to Indicated Mineral Resources,and achievement of the production target is uncertain.
A$1,038m
LOM free cash flow
A$618m
NPV8 (pre-tax)
61%
IRR (pre-tax)
52%
Margin
A$260m
Capex
2.4x
NPV8 (pre-tax) to
funding
A$39.70/oz
AISC
13 months
Payback
Paris DFS
Strong project economics to underpin valuations with direct leverage to silver
A$27m
Increase in NPV8 per
US$1/oz silver price
A$42m
Increase in free cash
per US$1/oz silver price
30Moz
LOM production
11 years
Initial mine life
US$60/oz
Price Assumption
0.69
Forex Assumption
9
Growth Beyond Current Pit
Today’s DFS is only the beginning
>30,000m drill
program underway
The DFS pit was deliberately constrained smaller than the optimized shell to limit Inferred material.
> 30,000m drill program in H2-26 targeting resource upgrade outside of existing pit and near-mine growth
within 15km.
Also, within the US$48/oz pit
shell, there is ~6Moz of silver
that makes margin at US$60/oz.
10
Growth Beyond Current Pit
Today’s DFS is only the beginning
2026 Preliminary Results:
Early assays show high
grades silver outside of pit¹:
• 10 m @ 2,662 g/t Ag
• 4 m @ 2,119 g/t Ag
• 5 m @ 426 g/t Ag
• 7 m @ 143 g/t Ag
• 9 m @ 110 g/t Ag
Extensions to the existing pit
through resource conversion
have potential to add silver
at low incremental cost
>30,000m drill
program underway
PPRC968 10m @ 2,662 g/t Ag from 78 m
inc. 1 m @ 13,302 g/t Ag
PPRC965 5m @ 426 g/t Ag from 49 m
inc. 1 m @ 1,545 g/t Ag
PPRC957 2m @ 4,211 g/t Ag from 111 m
inc. 1 m @ 8,120 g/t Ag
PPRC983 7m @ 143 g/t Ag from 34 m
PPRC948 9 m @ 110 g/t Ag from 81 m
¹ ASX announcement 9 November 2026.
² Drill results in figure above from ASX announcement1 September 2026.
11
District Scale Opportunity
Paris sits within a 15km underexplored mineralised corridor
Multiple near-pit prospects
provide potential for additional
silver discoveries beyond Paris, for
example:
• Apollo - 8m @ 1,262 g/t Ag¹
• Ares - 2m @ 243 g/t Ag²
• Athena - 20m @ 160 g/t Ag³
7m @ 111g/t Ag
5m @ 493 g/t Ag
¹ ASX announcement 25 August 2022. ² ASX announcement 27 October 2021. ³ ASX announcement 22 July 2025.
>30,000m drill
program underway
12
Lachlan Wallace | Managing Director
Led development of Kanmantoo underground
copper mine in SA from exploration to positive
cash flow through operations on time and
budget
Joe Sutanto | CFO & Company Secretary
Led commercial and financing of the
Kanmantoo underground copper mine
development in SA
Jason Murray | Exploration Manager
~6Moz of gold discoveries in Africa
Led Paris MRE growth to 57Moz and growing
Milan Jiranek | Project Director (construction)
Designed and developed the infrastructure at
Peak Iron’s Gawler Craton operations
Geoff Deans | Project Director (technical)
Led the $1.25b Oz Mineral’s Carrapateena Block
Cave Expansion in SA. Advising in consulting
capacity.
Byron Gordon | Chief Development Officer
Corporate finance and project funding executive
with over 20 years’ experience in the resources
sector, transitioning advanced-stage ASX projects
from development to production
Management team that builds mines
Proven experience in permitting, engineering, financing, constructing and operating mines in SA
13
Clear pathway to first silver
2026 2027 2028
Definitive Feasibility Study
Permitting
Drilling to de-risk start-up
Execution readiness
FID
Long lead
Construction
Silver production
14
Leverage to favourable silver market dynamics
Located in tier 1 jurisdiction with simple mining and processing
DFS confirms strong project economics
Management team are proven mine builders in South Australia
Trading at a significant discount to global silver peers
Investment Proposition
Silver is scarce. Quality projects are scarcer. The valuation disconnect is the opportunity
15
Lachlan Wallace | Managing Director
Level 1, 136 Greenhill Road,
Unley, SA, 5061
+61 (08) 7325 2222
Lwallace@ivrsilver.com.au
www.ivrsilver.com.au
16
Purpose and scope
This presentation has been prepared by Investigator Silver Limited (ACN 115 338 979, ASX: IVR) (the Company) to provide a general update on the Company and its projects. The information is a summary and is current as at the date of this presentation
unless otherwise stated. It should be read together with the Company’s announcements and periodic reports lodged with ASX.
No offer or financial product advice
This presentation is for informationpurposes only. It does not constitute an offer, invitation or recommendation to acquire, sell or hold securities or other financial products, or constitute financial product, investment, legal or tax advice. It has been
prepared without taking into account any person’s objectives, financial situation or needs. Investors should make their own assessment and seek independent professional advice before making an investment decision.
Forward-looking statements and investment risk
This presentation contains forward-looking statements, including development plans, project schedules, production targets and financial forecasts. These statements are based on assumptions and expectations at the date they are made and are
subject to risks and uncertainties, including exploration and technical outcomes, permitting, access to funding, construction and operating costs, commodity prices and exchange rates. Actual results may differ materially. Investors should avoid
placing undue reliance on forward-looking statements. Past performance is not a reliable indicator of future performance.
Paris DFS production target and forecasts
The Paris Silver Project production target and forecast financial informationderived from it are sourced from the Company’s ASX announcement dated 27 February 2026, Paris Silver DFS Confirms High-Margin, Finance-Ready Development Pathway;
Maiden Ore Reserve Declared. The Company confirms that all material assumptions underpinning the production target and the forecast financial informationderived from it continue to apply and have not materially changed.
The DFS production target comprises 86% Indicated Mineral Resources and 14% Inferred Mineral Resources. Inferred Mineral Resources carry a low level of geological confidence. Further exploration may not result in the conversion of Inferred Mineral
Resources to Indicated Mineral Resources, and there is no certainty that the production target will be achieved.
Reliance and liability
The Company has prepared this presentation in good faith using information available to it. To the maximum extent permitted by law, the Company and its directors, officers, employees and advisers make no representationor warranty as to the
accuracy, completeness or reliability of the informationand disclaim liability for loss arising from its use or reliance on it. Except as required by law or the ASX Listing Rules, the Company undertakes no obligation to update this presentation.
Currency
All monetary amounts are in Australian dollars unless otherwise stated. Figures may be rounded.
Important Information
17
Competent PersonStatements
Exploration Results: The information in this Presentation relating to Exploration Results is based on, and fairly represents, information and supporting documentation prepared by Mr Jason Murray who is a Member of the Australasian Institute of Mining and
Metallurgy (AusIMM) and a full-time employee of the Company. Mr Murray has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity being undertaken, to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Murray consents to the inclusion in this Presentation of the matters based on his information in the form and context in which it
appears.
Mineral Resource Estimates: The information in this report that relates to Mineral Resource Estimates at the Paris Silver Project is extracted from the release titled “Paris Mineral Resource Estimate Update” dated 5 July 2023 and is available to view on the
Company’s website. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement, and that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original
market announcement.
Ore Reserves: The information in this Presentation that relates to Ore Reserves is based on, and fairly represents, information and supporting documentation prepared by Mr Atish Kumar, who is a member of the Australasian Institute of Mining and Metallurgy
(AusIMM) and a consultant to the Company and is employed by Perth Mining Consultants. Mr Kumar has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity being undertaken, to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Kumar consents to the inclusion in this Presentation of the matters based on his information in the form
and context in which it appears.
Metallurgy: The information in this report that relates to metallurgical results is based on, and fairly represents, information and supporting documentation prepared by Mr Matthew Leske who is a member of the Australasian Institute of Mining and Metallurgy
(AusIMM) and a consultant to the Company and is employed by Ammjohn Solutions. Mr Leske has sufficient experience relevant to the style of mineralisation and type of deposit under consideration, and to the activity being undertaken, to qualify as a
Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Leske consents to the inclusion in this Presentation of the matters based on his information in the form
and context in which it appears.
The information in this Presentation that relates to the drill results is extracted from the release titled “Paris Regional Exploration Drilling Results” dated 25 August 2022, release titled “Silver Intersected Proximal to Paris Project” dated 30 May 2024, release
titled “Drilling Results From Greater Paris Silver Project” dated 31 March 2025, release titled “Quarterly Activities Report 30 September 2024” dated 23 October 2024, release dated “Earn-In agreement to silver opportunity next to Paris” dated 1 April 2025,
release titled “New Silver Intersection Identified at Athena” dated 22 July 2025, release titled “High-Grade Silver Discovery at Uno Morgans Project” dated 7 July 2022, and release titled “Paris Project Initial Silver Drill Results” dated 1 September 2026, and is
available to review on the Company’s website www.investres.com.au. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcements continue to apply and have not materially changed. The company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from the original market announcement.
Table 1: ParisMineral ResourceEstimate#1 Table 2: ParisOre Reserve Estimate#2
#1 – ASX announcement5 July 2023 Paris Mineral Resource Estimate Update
#2 – ASX announcement27 February Paris DFS Confirms Maiden Ore Reserve,Strong Economics
Category Mt Ag g/t Pb % Ag Moz Pb Kt
Indicated 17 75 0.5 41 85
Inferred 7.2 67 0.42 16 14
Total 24 73 0.41 57 99
Table 1: 2023 Paris Silver Project Mineral Resource estimate (25g/t silver cut-off grade).
(Note: Total values may differ due to minor rounding errors in the estimation process)
Category Mt Ag g/t Ag Moz
Proven - - -
Probable 12 88 33
Total 12 88 33
Table 2: 2026 Paris Silver Project Ore Reserve Estimate (Variable cut-off grade based on
geometallurgical domains:BT: 28.5g/t, BTM 24g/t, DOL 23g/t)
Important Information
Share your feedback
Discover