Half Yearly Accounts
Released
Released
Announcement PDF
Investigator Resources Limited
ABN 90 115 338 979
Half Year Financial Report - 31 December 2023
Investigator Resources Limited
Contents
31 December 2023
Corporate directory
Directors' report
Auditor's independence declaration
Statement of profit or loss and other comprehensive income
Statement of financial position
Statement of changes in equity
Statement of cash flows
Notes to the financial statements
Directors' declaration
Independent auditor's review report to the members of Investigator Resources Limited
1
2
3
15
16
17
18
19
20
28
29
Investigator Resources Limited
Corporate directory
31 December 2023
Directors
Richard Hillis – Non-Executive Chair
Andrew McIlwain – Managing Director
Andrew Shearer – Non-Executive Director
Company Secretary
Ms Anita Addorisio
Principal place of business
47 King Street
Norwood SA 5067
Share register
Computershare Limited
Level 5, 115 Grenfell Street
Adelaide SA 5000
Auditor
Grant Thornton Audit Pty Ltd
Level 3, 170 Frome Street
Adelaide SA 5000
Solicitors
Baker & McKenzie
L19, CBW, 181 William Street
Melbourne VIC 3000
Stock exchange listing
Investigator Resources Limited shares and options are listed on the Australian
Securities Exchange (ASX code: IVR and IVRO)
Website
Website: www.investres.com.au
2
Investigator Resources Limited
Directors' report
31 December 2023
The Directors present their report, together with the financial statements, on the consolidated entity (referred to hereafter as
the 'consolidated entity') consisting of Investigator Resources Limited (referred to hereafter as the 'Company' or 'parent entity')
and the entities it controlled at the end of, or during, the half-year ended 31 December 2023 (the 'financial half-year' or the
'interim reporting period').
Directors
The following persons were Directors of Investigator Resources Limited during the whole of the financial half-year and up to
the date of this report, unless otherwise stated:
Richard Hillis - Non-Executive Chair
Andrew McIlwain - Managing Director
Andrew Shearer - Non-Executive Director
Principal activities
The principal activity of the Group during the year was mineral exploration.
Dividends
There were no dividends paid, recommended or declared during the current or previous financial half-year.
Review of operations
The loss for the consolidated entity after providing for income tax amounted to $739,327 (31 December 2022: $857,372).
The net result for the financial half-year includes receipts of interest and other income of $85,954 (31 December 2022:
$46,489).
During the period, the Company incurred $2,303,435 expenditure on exploration activities across the Company’s tenements,
compared to $2,628,915 for the prior corresponding period. The exploration activity spend includes resuming its exploration
activities across the Uno Range and Morgans tenements in addition to the continuing work undertaken on advancing the Paris
Silver Project during the prior corresponding period. In the current period, the Company's spend was mainly towards Paris
Silver Project along with the continuing work undertaken on other tenements, as detailed in the project summary within this
report.
At 31 December 2023, the Company had a cash position of $5,511,442.
3
Investigator Resources Limited
Directors' report
31 December 2023
The main activities during the half year included:
Paris Silver Project
The Company’s 100% owned Paris Silver Project is located approximately 70km north of the rural township of Kimba
on South Australia’s Eyre Peninsula. Access to the project site is predominantly via highways and sealed roads and
is approximately 7 hours by road from Adelaide, as can be seen in the figure below.
Figure 1: Locality map showing Investigator’s SA tenements and Paris Silver Project – approximately 535km by
road, NW of Adelaide.
One of the highest grade undeveloped primary silver projects in Australia, the Paris Silver Project hosts a JORC
(2012) compliant Mineral Resource Estimate of 24Mt @ 73g/t silver and 0.41% lead for 57Mozs silver and 99kt lead
at a cut-off of 25g/t silver1. Paris is a shallow, high-grade silver deposit amenable to simple open pit mining and
currently in the process of undergoing Definitive Feasibility Study (DFS) studies to evaluate the project in advance
of any future development decision.
1 - As announced to the ASX on 5 July 2023
4
Investigator Resources Limited
Directors' report
31 December 2023
Paris Definitive Feasibility Study
Following on from completion of the updated Paris Silver Project Mineral Resource Estimate (ASX: 5 July 2023) the
Board of Investigator initiated a number of additional programs of work to inform a Definitive Feasibility Study on
Paris to be completed during the first half of 2024.
Table 1: 2023 Paris Silver Project Mineral Resource Estimates
Notes to be read in conjunction with the MRE above:
Based on 25g/t silver cut-off grade.
Values may not sum due to rounding.
Density: Indicated - 2.25t/m3, Inferred - 2.39t/m3 and Average - 2.30t/m3
The Company confirms that it is not aware of any new information or data that materially affects the Paris Silver
Project Mineral Resource, since its release in July 2023.
The 2021 Pre-Feasibility Study (PFS)2 highlighted the low-risk nature of the high-grade, near surface, open pit project
with the Base Case Scenario (“Whole of Ore Leach”) assuming a simple processing circuit with robust silver
recoveries. Importantly, this Base Case contemplated only recovery of silver with no revenue contribution from the
substantial lead contained in the resource included.
During the half-year period, work was undertaken to advance the Definitive Feasibility Study in the following areas.
Environmental
In the September Quarter 2023 Investigator Resources appointed JBS&G to commence a program of work to satisfy the
environmental requirements for the proposed Paris Silver Project Mining Lease application with the South Australian
regulators at the Department for Energy and Mining.
JBS&G undertook a gap analysis of the existing project reports and data held by Investigator and identified a number of
key areas where additional data collection would greatly assist in assessing the Project’s environmental risk and streamline
the approvals process.
One work component saw the completion of a comprehensive flora and fauna survey covering the Project’s proposed
footprint. Whilst a detailed baseline study had been completed in 2013, the 2023 survey closed off a number of important
aspects, including allowance for seasonal variation (a spring survey), in addition to acknowledging recent changes in the
Federal Environment Protection and Biodiversity Conservation Act and the Native Vegetation Act and Native Vegetation
Regulations (2017), as well as declared plants under the Landscape South Australia Act (2016).
The updated flora and fauna survey values were reported to be generally consistent with those observed and reported
within the 2013 baseline survey. No critical habitats for any nationally threatened species were reported as observed within
the project footprint, and habitat for state threatened species was widespread and regarded by the ecologists as unlikely
to be impacted by the project footprint or cause a reduction in species distribution.
Additional environmental components of work are ongoing, including weather, baseline dust monitoring, baseline noise
studies and additional soil geochemical baseline data for key project footprint areas that will provide valuable support in a
Mining Lease application for the Project.
Metallurgy
Metallurgical studies to optimise lead recovery and process plant design continued during the half-year period and are in
the final phases of test work prior to consideration of changes to the proposed process flowsheet. Importantly, the PFS
was undertaken on a silver only processing stream, the ability to identify and quantify what lead may be able to be recovered
from Paris as part of the DFS study will have important impacts on the process, mining and financial metrics for the project.
2 - As announced 30 Nov 2021
5
Investigator Resources Limited
Directors' report
31 December 2023
Outcomes from this lead recovery study will assist additional major milestones for the project, including mine design,
optimisation and scheduling, in addition to financial outputs of the study and is anticipated to be completed in early 2024.
An additional series of metallurgical samples were selected and aimed at assessing the variability within the Paris deposit.
“Like populations” were identified utilising the substantial geochemical dataset for the deposit and utilising X-Ray Diffraction
mineralogy. Machine learning was used to identify cluster populations of mineralisation having different gangue (or waste)
composition. Leach test work on these different clusters will allow metallurgical consultants to determine the relative effect
each different gangue composition may have on recovery in addition to grind and chemical/reagent use. This work will
provide confidence in the processing model and allow for any identified variability to be accounted for in design, scheduling
and financial modelling. This variability study is expected to be completed in early 2024.
Hydrology
Investigator completed a hydrological drilling program to determine the hydrological conditions surrounding the Paris
deposit, in addition to evaluating the Hector Paleochannel as a potential process water supply option for the project in the
second half of 2023, with data gathered from this body of work used in modelling of the Paris open pit hydrology, during
the half-year period. This body of work is in its final stages of review.
The final outputs from the Paris hydrology study will provide model estimates on water volume from staged pit dewatering
activities. This information will be utilised within the site water budget, with the objective of utilising the open pit water,
minimising additional water requirements for process plant use.
Modelling of the Hector Paleochannel is also in final stages of review. This phase of work was focussed on demonstrating
that the previously identified water source had the capacity to support required volumes throughout the lifetime of the
project for processing and ancillary purposes without a detrimental effect on the regional water table. These outputs will
similarly be used to construct a water budget for the project.
Geotechnical Studies
A review of draft geotechnical modelling which was completed during the half-year period by independent consultants,
Neboro is underway and this work will form the basis of future mine optimisation and design work as part of the DFS. It is
expected that finalisation of this work will be dependent on additional review of hydrological outputs discussed briefly
above.
Engineering Design and Cost Estimation
During the half-year period, Investigator identified additional consultants to assist in engineering design aspects of both
Plant and Mine and Civil operational aspects, in addition to cost estimation and financial modelling components. These
bodies of work will be developed over coming months once impacts of the Lead and Silver recovery study are known.
Community
Engagement with local and broader communities, as well as with the associated regulatory bodies also forms a vital
element of the DFS. Investigator recognises that best practice environmental management and strong support from
the community are critical to the Project’s success.
Dialogue with the Gawler Ranges Aboriginal Corporation (GRAC) continue with the objective of negotiating the Native
Title Mining Agreement (NTMA) necessary for the production phase of the Paris Project. GRAC are key stakeholders
in the advancement of Paris, and it is intended that they will also be beneficiaries of the Project’s successful
development.
It is anticipated that the Paris Silver Project’s Definitive Feasibility Study will be completed and announced to the ASX
in the first half of 2024.
Molyhil Tungsten Project
In November 2022 Investigator entered an heads of agreement to earn up to an 80% interest in the advanced Molyhil
Tungsten-Molybdenum Project in the Northern Territory3. Under the agreement expenditure of $1M on the Molyhil
Project gives Investigator the right to a 25% interest in Molyhil and surrounding exploration tenure, and 40% of the
adjacent Bonya tenement. Two further stages of expenditure of up to $7M over 6 years give the ability to earn an 80%
Molyhil project interest.
3 - As announced to the ASX – 24 Nov 2022 – “IVR enters Earn-In Agreement over Molyhil Tungsten Project
6
Investigator Resources Limited
Directors' report
31 December 2023
The Molyhil Project is located approximately 230km northeast of
Alice Springs, just off the Plenty Highway, as seen in Figure 1. The
project has historic mine production (1980’s) and substantial
project study work by Thor Energy PLC. The Molyhil TungstenMolybdenum Project has an existing Mineral Resource Estimate of
4.38Mt at 0.27% WO3 and 0.10% Mo for 11.8kt WO3 and 4.4kt Mo
(JORC 2012)4 and positive Definitive Feasibility Study5 results
which saw the project granted Major Project Status6 by the NT
Government.
Figure 2: Location of Molyhil in the NT
With Major Project Status granted, and two critical minerals, Molyhil is set to benefit from streamlined regulatory approvals,
in addition to exposure to potential funding opportunities given the strategic importance of these minerals, reinforcing the
project’s path towards a future potential mining operation.
Work completed during the half-year period included a significant amount of approvals and logistical planning in advance
of Investigators maiden resource drill program at Molyhil.
Table 2: Molyhil MRE classification as reported by Thor Energy to the ASX on 8 April, 2021.
Molyhil Resource Drill Program
Thirteen diamond drill holes were drilled for a total of 1,350m during November and early December 2023. Drilling design
was undertaken in consultation with the Company’s independent mineral resource estimation consultant engaged for this
project work.
All drill core was comprehensively logged in the field, including sample markup prior to dispatch for core cutting and sample
preparation. Samples for the program were subsequently freighted to Investigator’s preferred independent laboratory for
analysis for tungsten, molybdenum and a comprehensive suite of additional elements. All samples are in the process of
being tested, with results anticipated to be returned during February 2024.
In tandem with this work, Investigator’s geologists are working through detailed QA/QC analysis and documentation to
support the pending updated Mineral Resource Estimate. This work includes geological reinterpretation, documentation
and evidence support of procedures, in addition to eventual analysis of twinned historic holes, analytical standards and
similar aspects.
On completion of this body of work (shortly after receipt of final assay data), the independent resource consultant will
undertake a re-estimation of the Molyhil Mineral Resource. The results of this work will provide the Investigator Board a
base to consider future investment timing in the project.
4 - As reported by THR to the ASX – 8 Apr 2021
5 - As reported by THR to the ASX – 23 Aug 2018
6 - As reported by THR to the ASX – 6 Jul 2020
7
Investigator Resources Limited
Directors' report
31 December 2023
Molyhil Metallurgical Review
During the half-year period, Investigator engaged consultant metallurgists experienced in tungsten processing to undertake
a review of prior metallurgical process work undertaken by Thor Energy Plc. This review was aimed at identification of any
potential process opportunities to exploit, as part as an initial gap analysis. This work is not yet complete, but is expected
to be available for consideration by Investigator’s Board at the time that future investment decision is made when the
updated Mineral Resource Estimate is announced.
Co-funded Gravity Survey
During the half-year period a gravity survey, co-funded by the NT Government, was completed at Molyhil, marking a
significant step in refining the exploration strategy. A total of 3,506 gravity stations were completed.
Other than a broad spaced historic coverage (2km x 2km), no detailed gravity surveys have been undertaken across the
Molyhil Project or the surrounding area. The survey, conducted on spacings varying from 200m x 100m, down to 20m x
40m in some areas, will provide high resolution gravity data over the Molyhil deposit and its surrounding area, as shown in
Figure 3.
Early in Investigator’s due diligence review, observations of strong density contrast between geological sequences within
the Molyhil Deposit, and due to dense tungsten/molybdenum mineralisation, saw a proposal developed to complete gravity
surveying within the tenement as a method to map geological units under cover, and identify areas of particularly high
density that may represent additional, undiscovered mineralisation.
Figure 3. Location of the Molyhil project over regional 2km x 2km spaced gravity data. Note the Molyhil Project is on
the margin of a large gravity low anomaly.
As at the time of reporting, all gravity data and collection reports have been received by Investigator, with data levelling
and modelling activities being undertaken by the company’s consultant geophysicist. The results of this survey,
including additional target opportunities are expected to be reported in the March 2024 Quarter.
8
Investigator Resources Limited
Directors' report
31 December 2023
Other Investigator Tenements
Native Title Negotiations
Investigator have been successful in applying for and being granted a number of tenements within the East Eyre and
Stuart Shelf regions over the past 2 years. In order to undertake exploration activities, there has been a requirement to
negotiate to add tenements to existing NTMA’s or negotiate new agreements to allow exploration activity on ground to
occur. Tenements requiring this included Siam, Lake Macfarlane, Wartarka, Harris Bluff, Corunna, Yardea, Nonning
South, Uneroo and Kootaberra. Three differing Aboriginal Corporations either cover a part or whole of the tenements
listed above and have been engaged with by Investigator to allow exploration to commence.
A meeting and presentation with the Kokatha Aboriginal Corporation (RNTBC) (KAC) Registered Native Title Board
(RNTBC) was held during the half-year period. Following the presentation by Investigator, the KAC members and board
voted to allow a number of new tenements in this region to be added to the existing NTMA agreement between
Investigator and KAC. This agreement has significantly streamlined Investigator’s ability to explore on the ground in
these areas, where part of the KAC determination area. These tenements include Kootaberra, Uneroo and Lake
Macfarlane (part).
Additional new tenements within the East Eyre and Stuart Shelf areas were also incorporated into a new NTMA with
the Gawler Ranges Aboriginal Corporation (GRAC) RNTBC, similarly opening opportunity to undertake on ground
exploration. Tenements added to the GRAC NTMA include Siam (part), Nonning South, Yardea and Harris Bluff.
Negotiations are pending for Corunna, Wartarka, Siam (part) and Lake Macfarlane (part) with the Barngarla
Determination Aboriginal Corporation (BDAC) RNTBC and will continue to be pursued by Investigator.
Investigator Resources would like to acknowledge all of the Aboriginal groups on whose land we live and work.
Wartarka/Lake Macfarlane/Uneroo/Siam EL’s
In addition to NTMA negotiation, significant review of legacy data has occurred, combined with the planning for field
activities on a series of areas that are accessible with new agreements in place. Initial field orientation and targeted
soil sampling in a number of identified areas will occur in early 2024 where agreements are in place.
As a result of these data reviews, an additional tenement to the west of Lake Macfarlane, named Nonning was applied
for, after identifying evidence of prospectivity for lead, zinc and copper within historic exploration records.
Curnamona
Limited work occurred in the Curnamona area during the half-year period due to high workload on other project areas.
The company has compiled all recent soil and rock chip data from the Curnamona project area, in addition to drone
magnetics and is in the process of development of drill target prioritisation for review.
Uno Range/Morgans/Harris Bluff/Nonning South/Yardea EL’s
During the half-year period, the major component of work was negotiation of a new NTMA covering these tenements
with the GRAC. This has allowed work on Nonning South and Yardea to commence, with a first phase of mapping and
reconnaissance soil sampling completed during the half-year period. Results of the soil sampling are in the process of
being reviewed to prioritise additional early evaluation of these two tenements.
Additional follow up evaluation of the Uno Range/Morgans and Harris Bluff tenements has been delayed due to high
workload at Paris and Molyhil. Reviews of prior drilling and a small program of additional soil coverage has taken place
and proposals for additional follow up drilling are being reviewed.
Fowler Domain
During the half-year period Osmond Resources completed a helicopter supported gravity survey on IVR’s 100% owned
Fowler Domain tenements that are subject to a Earn-In to Joint Venture agreement. Osmond have announced that the
recently completed gravity survey has been modelled and integrated with historic detailed aeromagnetic and VTEM
survey data, identifying high priority targets for follow up exploration in 2024, which may involve follow up Moving-Loop
Electro Magnetic (MLEM) survey and ultimately drill testing7.
7 - As reported by OSM – 19 Dec 2023
9
Investigator Resources Limited
Directors' report
31 December 2023
Stuart Shelf
As at the end of September, 2023, Gold Road Ltd (ASX:GOR) had spent approximately $2.5M in their earn-in to
Investigators Stuart Shelf Tenements. Having satisfied the Stage 2 commitment of $2M, GRO have notified Investigator
of their intention to form the 51:49 Joint Venture interest in the tenements. Application to transfer the 51% interest
earned in the Joint Venture tenements to GOR has been lodged with the Department for Energy and Mining and is being
processed.
Tasmania – White Spur – EL2/2020
Investigator holds the White Spur exploration licence (EL2/2020) in the highly mineral endowed Mount Read Volcanic
belt of North-West Tasmania.
Identified through a “machine learning” or “neural analysis” exercise in targeting mineralisation similar to that at the
significant Rosebery Mine (which has operated continuously from 1936, producing zinc, copper, lead and gold) and
Henty Mine (produced approximately 1.3Moz since its commissioning in 1996), the 84km2 White Spur tenement lies
immediately to the south of the Rosebery and historic Hercules zinc mines and west of, and adjacent to the Henty
Mine.
No significant exploration has been undertaken on the tenement since 2013 when the presence of thallium, a known
vector to massive sulphide mineralisation, was reported.
No additional work was undertaken during the half-year period by Investigator due to other high priority commitments.
10
Investigator Resources Limited
Directors' report
31 December 2023
Corporate disclosure and reporting
The status of Investigator’s tenements at 31 December 2023 are detailed in the table below:
11
Investigator Resources Limited
Directors' report
31 December 2023
CORPORATE
Business Risks
Investigator’s operating and financial results and performance are subject to various risks and uncertainties, some of
which are beyond Investigator’s reasonable control. Set out below are matters which the Group has assessed as having
the potential to have a material impact on its operating and/or financial results and performance:
(i) Fluctuations in external economic drivers including macroeconomics and metal prices: The consolidated
entity’s primary focus is the advancement of its Paris Silver Project. Fluctuations in the silver price can result from
various aspects beyond Investigator’s control, including macroeconomic and geopolitical. Sustained lower silver
prices would adversely impact the viability of the Project.
(ii) Capital and Liquidity: The consolidated entity will incur expenditures over the next several years in connection with
its exploration objectives and development of new projects and relies on its ability to raise capital as its primary
source of funding. The company is exposed to the risk that unfavorable macroeconomic and market conditions would
preclude it from raising sufficient capital.
(iii) Failure to discover mineral resources and convert to ore reserves: Exploration activities are speculative in
nature and often require substantial expenditure on exploration surveys, drilling and sampling as a basis on which to
establish the presence, extent and estimated grade (metal content) of mineralised material. Even if significant
mineralisation is discovered, it may take additional time and further financial investment to determine whether a
mineral resource has attributes that are adequate enough to support the technical and economic viability of mining
projects and enable a financial investment and development decision to be made. During that time the economic
viability of the project may change due to fluctuations in factors that affect both revenue and costs, including metal
prices, foreign exchange rates, the required return on capital, regulatory requirements, tax regimes and future cost
of development and mining operations.
(iv) Renewal of tenements: The consolidated entity has been granted tenements by the South Australian Department
for Energy and Mining (‘the Department’) on the terms and conditions set out in the related lease agreements. At
the expiry of the lease term, the decision of renewal application to assign tenements to the consolidated entity
remains with the Department. A non-renewal of a tenement would adversely affect the operational results and
fulfilment of the aspirations of the consolidated entity.
(v) Failure to attract and retain key employees: The consolidated entity is heavily dependent for its continued
operational success on its ability to attract and retain high calibre personnel to fill roles including Directors, Managing
Director, Exploration Manager and geologists. A loss of key personnel or a failure to attract appropriately skilled and
experienced personnel could affect its operations and performance.
Business Development
The Company continues to review opportunities for access to and or acquisition of projects within the domestic precious
metals area, with a target profile of late-stage exploration through pre-development to production. The Investigator team
has continued to actively review and assess acquisition opportunities.
Whilst market conditions are such that identifying potential acquisitions with compelling accretive value prospects is
challenging. We, the Company remain committed to a disciplined process and evaluation in this pursuit.
12
Investigator Resources Limited
Directors' report
31 December 2023
Corporate Placement
On 13 December 2023, the Company announced that it had received firm commitments to raise $5 million through a share
placement to raise $4 million from institutional and sophisticated investors (Placement) and a share purchase plan fully
underwritten for $ 1 million. Funds raised will be used for the completion of the Paris Silver Project Definitive Feasibility Study
(DFS), further exploration of the Peterlumbo tenement that hosts Paris and exploration activities across the Company’s 100%
owned regional tenements.
The Placement constituted the issue of 102 million new fully paid ordinary shares in the Company at 3.9c per share, being
approximately a 15% discount to the last previously traded price of 4.6c per share.
For every 2 shares subscribed for in the Placement, one listed IVRO option was issued with an exercise price of 6.3c per
option, expiring in March 2025.
Additionally, a share purchase plan (SPP) was offered to shareholders on the register on 12 December 2023. The SPP was
fully underwritten to $1 million and was offered on identical terms to the Placement. For every 2 shares issued under the SPP,
1 listed option was also issued.
In addition, the secondary purpose of the Prospectus provided for the issue of 51,282,052 Placement Options and 12,628,205
Broker Options following the Placement as announced on 19 December 2023 at a zero application price which were subject
to shareholder approval.
The SPP closed on 15 January 2024 and was oversubscribed raising approximately $1.72 million with a total of 44,145,453
shares and 22,072,816 IVRO options issued to subscribing shareholders.
The 51,282,052 Placement Options and 12,628,205 Broker Options were approved at a shareholders meeting held on 25
January 2024 and issued on 30 January 2024.
Competent Person Statement
The information in this Half Year Report that relates to exploration results is based on information compiled by Mr. Jason
Murray who is a full-time employee of the company. Mr. Murray is a member of the Australasian Institute of Mining and
Metallurgy. Mr. Murray has sufficient experience of relevance to the styles of mineralisation and the types of deposits under
consideration, and to the activities undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint
Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves. Mr. Murray consents to the inclusion in this report of the matters based on information in the form and context in
which it appears.
The information in this release that relates to Mineral Resources Estimates at the Paris Silver Project is extracted from the
release
Share your feedback
Discover