Investigator Silver Limited | ABN: 90 115 338 979 | Level 1, 136 Greenhill Road, Unley SA 5061 Australia | ASX: IVR | www.ivrsilver.com.au Page | 1
INVESTIGATOR DELIVERS KEY DEVELOPMENT MILESTONES AT PARIS AND COMMENCES
30,000 METRE DRILLING PROGRAM
30 October 2026
Investigator Silver Limited
Quarterly Activities Report
Period Ending 30 September 2026
HIGHLIGHTS
• Mining Lease Application lodged for the Paris Silver Project, marking a major milestone in
advancing the Project through the South Australian approvals process1.
• High-grade drilling results returned outside the current DFS mine plan, highlighting
opportunities to increase the Paris mining inventory and further enhance project value2.
• Fully funded 30,000m drilling program commenced, targeting resource growth, resource
confidence conversion and extensions to mineralisation beyond the current DFS mine plan3.
• Continued progress across engineering, project execution and financing readiness activities,
supported by further strengthening of the Company's project delivery capability.
• Strong cash position of $55.1m at 30 September 2026.
MANAGING DIRECTOR’S COMMENT
Investigator Silver’s Managing Director, Lachlan Wallace, commented on the quarter:
“The September quarter delivered another important step forward for the Paris Silver Project as we
continued to derisk the Project. The lodgement of our Mining Lease Application marked a
significant milestone in advancing Paris through the South Australian approvals process, while
work continued on the Native Title Mining Agreement, land access and other key approval
workstreams required to support future development.
On the exploration front, the results released during the quarter continued to demonstrate the
quality and growth potential of the Paris mineralised system, with high-grade drilling results
returned outside the current DFS mine plan. These results reinforce our view that there remains
significant opportunity to increase the Paris mining inventory and further enhance project value.
As a result, it led to our decision to continue drilling aggressively over the coming quarters, with
the commencement of our fully funded 30,000 metre drilling program – the objective being to grow
the estimated Resource, improve its confidence, and incorporating these outcomes into an updated
1
Refer ASX announcement of 19 August 2026
2
Refer ASX announcement of 1 September 2026
3
Refer ASX announcement of 23 September 2026
ASX Release – Investigator Silver
Page | 2
Mineral Resource Estimate and project studies as we progress towards the final investment
decision.
With a strong balance sheet, an experienced team and multiple value enhancing workstreams
underway, we believe Investigator is well positioned to continue advancing Paris towards
development.”
PARIS PROJECT DEVELOPMENT
Permitting
The Company achieved a major permitting milestone during the quarter with the lodgement of the Mining
Lease Application (MLA) for the Paris Silver Project (as announced to the market on 19 August 2026). The
MLA follows extensive technical, environmental and stakeholder consultation work and advances Paris
through the South Australian approvals process. The application has progressed into the assessment and
community consultation phase, marking the commencement of the regulatory review process required
for the grant of a Mining Lease.
Significant effort during the quarter was directed towards stakeholder engagement, native title
discussions and the continued development of environmental and operational management frameworks
that will support future regulatory approvals and project development activities – with the Company
working closely with government agencies, Traditional Owners and landholders.
These activities form part of the Company's strategy to systematically derisk the approvals pathway,
reduce development risk and position Paris to move efficiently through the remaining stages of
permitting.
Project Execution
During the quarter, the Company continued to advance project execution activities aimed at transitioning
the Paris Silver Project from DFS to a development ready project. Activities completed or advanced during
the period included ongoing metallurgical testwork, site infrastructure planning, process design
optimisation, procurement planning and mine development studies. These workstreams are being
undertaken in parallel with the permitting process to ensure the Project continues to advance on multiple
fronts as it moves towards a development decision.
The Company also continued to work closely with its engineering and project delivery partners to refine
key aspects of the Project and evaluate opportunities identified through the DFS. Development of the site
layout progressed during the quarter, incorporating increasingly detailed infrastructure, haul road and
site access designs, while metallurgical and process optimisation studies continued to support future
engineering and financing activities.
ASX Release – Investigator Silver
Page | 3
EXPLORATION
Paris Silver Project
Exploration activities during the quarter focused on preparation and commencement of drilling at Paris
with drilling prioritised on areas where resource estimate conversion has potential, in addition to detailed
drilling to derisk the project by assessing grade continuity at short spacings.
Results from Paris East included 4m @ 5,448g/t Ag from 78m, including 1m @ 13,302g/t Ag, together with
2m @ 822g/t Ag from 49m and 3m @ 275g/t Ag from 91m and at Paris North, drilling returned 2m @
4,211g/t Ag from 111m, including 1m @ 8,120g/t Ag, together with broader mineralised intervals that
demonstrate potential to add near-mine ounces and increase the overall mining inventory4. Results from
Paris Deeps also confirmed the continuation of mineralisation beneath the current DFS pit design.
Figure 1: Paris Deposit H1 2026 RC drilling, showing historic drilling, 2026 DFS Paris optimised pit outline, main
targets and key results to date. cross-sections annotated for reference. Shown on satellite true colour image.
The Company commenced a fully funded approximately 30,000 metre drilling program during the quarter.
The program is designed to support conversion of mineralisation into higher confidence estimated
Resource categories and evaluate opportunities to expand mineralisation within and beyond the current
DFS mine plan. The drilling program will also provide important information for future mine planning and
financing workstreams as the Project advances towards a development decision.
This drill program commenced in late September, following weather related interruptions earlier in the
year, with 24 holes for approximately 2,900 metres completed by quarter end.
4
Refer ASX announcement of 1 September 2026
ASX Release – Investigator Silver
Page | 4
Regional Exploration
The Company continued to evaluate growth opportunities within the broader Paris Silver Corridor and
regional tenure. Geological mapping, target generation and regional exploration programs continued
throughout the quarter, with work focused on advancing a pipeline of drill ready targets capable of
supporting future resource growth beyond the Paris deposit.
A significant outcome from regional exploration was the identification of a new silver-bearing epithermal
system at the Theseus Prospect, located approximately 7.5km southeast of Paris. Sampling of historical
drill core returned multiple silver-bearing intervals associated with epithermal alteration and base metal
mineralisation, highlighting the prospectivity of the broader Paris Silver Corridor and providing an
attractive future exploration target.
Target generation and geophysical interpretation work continued, identifying additional opportunities for
future drill testing. These activities are aligned with the Company's strategy of growing the long-term
development pipeline and extending the scale of the Paris Silver Corridor.
Figure 2: H1 2026 RC drilling, showing historic drilling, key regional targets, 2026 DFS Paris Deposit pit outline,
tenure, the Paris Silver corridor, and Theseus cross-section location. Shown on colourised 1VD AMAG image.
ASX Release – Investigator Silver
Page | 5
CORPORATE ACTIVITIES
During the quarter, Investigator continued to strengthen its executive, technical and project delivery
capability to support advancement of the Paris Silver Project towards development. Key appointments
included Joe Sutanto as Chief Financial Officer and Joint Company Secretary, Byron Gordon as Chief
Development Officer, Luke Cerny as Principal Mining Engineer and Dr Ben Cave as Senior Exploration
Geologist. The Company also expanded its project delivery capability through the engagement of
specialist consultants across engineering, project execution, permitting and mine planning disciplines.
Together, these additions enhance the Company's capability to progress permitting, engineering,
financing and exploration activities as Paris advances towards a development decision.
The Company commenced preliminary discussions with potential funding providers and industry
participants during the quarter, while also progressing compilation of a project data room to support
future lender and investor due diligence processes. These activities form part of a broader financing
readiness program designed to position the Project for future financing activities as key permitting,
engineering and exploration workstreams continue to advance.
Cash Position
At 30 September 2026, the Company held a strong cash position of $55.1m.
Corporate Disclosure and Reporting
During the quarter, the Company:
• Invested $3.2m on exploration and evaluation activities as outlined within this report; and
• Paid Executive Director salaries and Non-Executive Director fees of $289k (as disclosed in sections
6.1 and 6.2 of the accompanying Appendix 5B).
OUTLOOK
In the coming quarter, the Company will continue to advance Paris towards a development decision,
focussing on:
• Permitting – advance the Native Title Mining Agreement, land access negotiations and PEPR
preparation, including detailed planning and engineering design activities, to further de-risk the
approvals pathway and support future development.
• Project execution – complete the power studies as well as advance metallurgical testwork,
engineering definition, mine planning and execution readiness activities, while continuing to
evaluate opportunities to optimise project outcomes and enhance value.
• Paris exploration – continue the fully funded 30,000 metre drilling program focused on Resource
growth, Resource confidence and expansion of the Paris mining inventory, while progressing
regional exploration opportunities across the broader Paris Silver Corridor.
• Project financing – continue advancing financing readiness initiatives, including engagement with
potential funding counterparties, development of due diligence materials and progression of
workstreams required to support a future financing process.
ASX Release – Investigator Silver
Page | 6
For and on behalf of the board.
Lachlan Wallace
Managing Director
For further information, please contact:
Lachlan Wallace
Managing Director
+ 61 (0) 8 7325 222
Joe Sutanto
Chief Financial Officer
+ 61 (0) 8 7325 222
ASX Release – Investigator Silver
Page | 7
ABOUT INVESTIGATOR SILVER
Investigator Silver Limited (ASX: IVR) is advancing its 100%-owned Paris Silver Project, located on South
Australia’s Eyre Peninsula approximately 70km north of Kimba.
Paris hosts a JORC 2012 Mineral Resource of 24Mt @ 73g/t Ag and 0.4% Pb for 57Moz silver and 99kt lead
(Indicated + Inferred), and a maiden Ore Reserve of 12Mt @ 88g/t Ag for 33Moz silver (Probable).
The Company has completed a Definitive Feasibility Study (DFS) for Paris, confirming a conventional, low
technical risk development pathway: a shallow open-pit orebody mined by contract mining, processed via
a whole-ore cyanide leach flowsheet with Merrill–Crowe doré recovery.
The DFS outcomes support a fundable project profile, characterised by strong operating margins and rapid
payback.
Investigator is now focused on progressing Paris from DFS into execution by advancing engineering,
approvals and early development activities, while continuing exploration to support mine expansion and
district-scale growth within the broader Paris region.
Capital Structure (as at 30 September 2026) Directors & Management
Shares on issue 2,622,857,752 Dr Richard Hillis Non-Exec. Chair
Listed Options (IVROB) 462,589,367 Mr Lachlan Wallace Managing Director
Mr Andrew Shearer Non-Exec. Director
Top 20 shareholders 38.21% Mr Joe Sutanto CFO & Joint CoSec
Total number of shareholders 8,129 Ms Anita Addorisio Joint Company Secretary
Total number of option holders (IVROB) 782
TENEMENT HOLDINGS AT THE END OF THE QUARTER
Tenement Number Location Tenement Name Registered Holder Ownership
Project: Peterlumbo (IVR 100%)
EL6347 Sth Aust Peterlumbo SUNTHE 100%
Project: Uno/Morgans (IVR 100%)
EL5845 Sth Aust Uno Range GRL 100%
EL5933 Sth Aust Morgans GRL 100%
EL6724 Sth Aust Corunna GRL 100%
EL6753 Sth Aust Nonning South GRL 100%
EL6725 Sth Aust Yardea GRL 100%
EL5913 Sth Aust Harris Bluff GRL 100%
EL6953 Sth Aust Eurilla Hill GRL 100%
Project: Curnamona (IVR 100%)
EL5938 Sth Aust Wiawera GRL 100%
EL6345 Sth Aust Treloars GRL 100%
EL6253 Sth Aust Olary/Bulloo Creek GRL 100%
Project: Northern Territory
EL29701 NT Bonya FRAM 40%
SUNTHE - Sunthe Minerals Pty Ltd, a wholly owned subsidiary of Investigator Resources Ltd.
ASX Release – Investigator Silver
Page | 8
GRL - Gawler Resources Pty Ltd, a wholly owned subsidiary of Investigator Resources Ltd.
FRAM - Fram Resources Pty Ltd, a wholly owned subsidiary of Investigator Resources Ltd.
COMPETENT PERSONS STATEMENT
The information in this report relating to Exploration Results is based on, and fairly represents,
information and supporting documentation prepared by Mr Jason Murray who is a Member of the
Australasian Institute of Mining and Metallurgy (AusIMM) and a full-time employee of the Company. Mr
Murray has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration, and to the activity being undertaken, to qualify as a Competent Person as defined in the
2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. The Company confirms that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original market announcement.
The information in this report that relates to Mineral Resource Estimates at the Paris Silver Project is
extracted from the release titled “Paris Mineral Resource Estimate Update” dated 5 July 2023, and
information in this report that relates to Paris Definitive Feasibility Study is extracted from the release
titled “Paris DFS Confirms Maiden Ore Reserve, Strong Economics” dated 27 February 2026. Both
announcements are available to view on the Company’s website. The Company confirms that it is not
aware of any new information or data that materially affects the information included in the original
market announcements, and that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcements continue to apply and have not materially changed. The
Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially modified from the original market announcement.
The information in this report that relates to Ore Reserves is based on, and fairly represents, information
and supporting documentation prepared by Mr Atish Kumar, who is a member of the Australasian
Institute of Mining and Metallurgy (AusIMM) and a consultant to the Company and is employed by Perth
Mining Consultants. Mr Kumar has sufficient experience relevant to the style of mineralisation and type
of deposit under consideration, and to the activity being undertaken, to qualify as a Competent Person as
defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral
Resources and Ore Reserves’. The Company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market
announcement.
Paris Mineral Resource Estimate5
Category Mt Ag g/t Pb % Ag Moz Pb Kt
Indicated 17 75 0.5 41 85
Inferred 7.2 67 0.42 16 14
Total 24 73 0.41 57 99
2023 Paris Silver Project Mineral Resource estimate (25g/t silver cut-off grade).
(Note: Total values may differ due to minor rounding errors in the estimation process)
5
ASX Announcement 5 July 2023 Paris Mineral Resource Estimate Update
ASX Release – Investigator Silver
Page | 9
Paris Ore Reserve Estimate6
Category Mt Ag g/t Ag Moz
Proven - - -
Probable 12 88 33
Total 12 88 33
2026 Paris Silver Project Ore Reserve Estimate (Variable cut-off grade based on geometallurgical
domains: BT: 28.5g/t, BTM 24g/t, DOL 23g/t).
(Note: Total values may differ due to minor rounding errors in the estimation process).
ASX announcements 5 July 2023 “Paris Mineral Resource Estimate Update” and 27 February 2026 “Paris
DFS Confirms Maiden Ore Reserve, Strong Economics”. The Company confirms that it is not aware of any
new information or data that materially affects the information included in the original market
announcements of 5 July 2023 and 27 February 2026, and that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have
not materially changed. The company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market
announcement.
6
ASX Announcement 27 February 2026 Paris DFS Confirms Maiden Ore Reserve, Strong Economics
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
INVESTIGATOR SILVER LIMITED
ABN Quarter ended (“current quarter”)
90 115 338 979 30 September 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (540) (540)
(e) administration and corporate costs (618) (618)
1.3 Dividends received (see note 3) - -
1.4 Interest received 669 669
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(489) (489)
2. Cash flows from investing activities
2.1 Payments to acquire:
(a) entities
(b) tenements - -
(c) property, plant and equipment (124) (124)
(d) exploration & evaluation (3,213) (3,213)
(e) investments (93) (93)
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
2.2 Proceeds from the disposal of: - -
(a) entities
(b) tenements 219 219
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities (3,211) (3,211)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(6) (6)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) - -
3.10 Net cash from / (used in) financing
activities
(6) (6)
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
58,760 58,760
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(489) (489)
4.3 Net cash from / (used in) investing activities
(item 2.6 above) (3,211) (3,211)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
(6) (6)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (3
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
55,054 55,054
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 14,565 18,751
5.2 Call deposits 40,489 40,009
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
55,054 58,760
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
289
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
0
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (489)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(3,213)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (3,702)
8.4 Cash and cash equivalents at quarter end (item 4.6) 55,054
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 55,054
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
14.9
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 30 October 2026
Authorised by: By the Board
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.