Quarterly Activities and Cash Flow Report
Released
Released
Announcement PDF
QUARTERLY
ACTIVITIES REPORT
30 June 2023
HIGHLIGHTS
OPERATIONAL
Exploration success from Paris South drilling - final 24 holes returned with best intercepts including:
–
Hole PPRC882 (Line -0.75)
25m @ 207g/t Silver from 73m; including
8m @ 615g/t Silver from 78m; including
1m @ 2,410g/t Silver from 80m
39m @ 80g/t Silver from 111m; including
Updated Paris Mineral Resource estimate post quarter end:
–
14m @ 177g/t Silver from 116m
57Mozs silver and 99kt lead
Drilling at Apollo continues to provide encouraging results with silver intersections and
native silver observed. Best intercepts include:
–
Hole PPRC892
–
Hole PPRC896
3m @ 34g/t Silver from 189m
3m @ 10g/t Silver, 9m @ 0.34% Lead, 12m @ 0.29% Zinc from 72m
Apollo petrological samples confirm shallow epithermal-type environment with multiphase metal bearing fluids.
Paris DFS Hydrology program completed identifying significant water bearing sands at
Hector. Pump drawdown and recharge testing underway.
Successful co-funding application for gravity survey program across the Molyhil tungsten Project in NT.
CORPORATE
Successful application for JMEI tax credits of $312,500
Cash at 30 June 2023 $4.5M
OPERATIONS
Paris Silver Project
Investigator’s principal asset is the 100% owned Paris Silver Project, located approximately 70km north of
the rural township of Kimba on South Australia’s Eyre Peninsula. Access to the project site is predominantly via highways and sealed roads and is approximately 7 hours by road from Adelaide, as seen in
Figure 1 (below). Major regional centres with industrial capacity, support services and airports are Whyalla
(212km) and Port Augusta (227km).
Paris is a shallow high-grade silver deposit amenable to open pit mining, providing outstanding
exposure to silver, a metal with strong commodity, renewable energy and manufacturing demand.
Post June quarter, Investigator released an updated JORC 2012 Mineral Resource estimate of
24Mt @ 73g/t silver and 0.41% lead for 57Mozs
silver and 99kt lead1. Paris Silver Project PreFeasibility Study reported financial results of: pretax NPV8 A$202M, pre-tax IRR 54.1% with capital costs of A$131M2&3. Comprehensive work program underway targeting completion of the Definitive Feasibility Study (DFS) in early 2024.
Figure 1: Investigator’s South Australian tenements
Investigator continues to progress exploration
across adjacent significant ground holdings
within South Australia and also a farm-in at the
Molyhil Tungsten Project in the Northern Territory.
Paris South Resource Extension Drilling Program
During the June Quarter final assay results were reported from the 7,150m drill program for 37 holes drilled
at Paris South. This program commenced in late November 2022 and covered a potential 250m extension
to the Paris Resource. This step-out drilling, targeting the southern strike extension is shown in Figure 2
(below).
Hole PPRC882 drilled in this zone returned significant silver intersections with 25m @ 207g/t silver from
73m, including 8m @ 615g/t silver from 78m, which included a new highest-grade silver assay for this
program of 1m @ 2,410g/t silver from 80m.
1 - ASX 5 July 2023 – “Paris Mineral Resource Update” (refer Appendix 1 for Resource Table).
2 - ASX 30 November 2021 – “Paris PFS delivers outstanding results”
ABN 90 115 338 979 | ASX: IVR | Page 2 of 15
PO Box 3235, Norwood SA 5067
+61 (0) 8 7325 2222 | info@investres.com.au
www.investres.com.au
3 - Note: Paris PFS completed on previous resource – as released
to ASX 30 Nov 2021
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Figure 2: Plan shows the previous drilling at the Paris Deposit overlying the 2021 estimated resource classification block model,
with the 2022/23 drill holes shown at Paris South (yellow collars). Section A-A’ through Line -3.0 is shown in Figure 3 below.
Figure 3 (below) shows Section A-A’ across Line -3.0, the southern-most line drilled in this program. Drilling
intersected ignimbritic volcanics bounded on the east of the section by metasediments with an interpreted
faulted contact associated with an intersection of 34m @ 48g/t silver from 61m, including 11m @ 90g/t
silver from 78m (PPRC881). Mineralisation on this section indicates scope for additional mineralisation
south of current drill coverage at Paris.
Page | 3
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Figure 3: Drill section A – A’ showing cross section of holes on Line -3.0 (refer Figure 2 above for section location). Hole traces
display geology with red bars identifying silver intersections above 10g/t and black bars identifying lead intersections above 0.1%.
Commentary
The results returned from the Paris South exploration program demonstrated the continuity of prospective
geology and confirmed the continued silver and lead mineralisation extending further south of the existing
Paris mineral resource estimate. Importantly, mineralisation remains open to the south providing scope for
further project growth.
Paris Silver Project – Updated Mineral Resource Estimate
Post quarter end, an updated Mineral Resource Estimate (Mineral Resource Estimate) was released to
the ASX4.
With the results from the drill program described above, in addition to further confirmatory drilling, a total
of 76 holes drilled since the 2021 resource update were included in this latest Mineral Resource Estimate.
Whilst the majority of these holes targeted the potential resource extension to the south of Paris, additional
exploration drilling was completed along the western and eastern flanks of the deposit as well as in the
central zone of the resource - located between the optimised northern and southern pits.
4 - ASX 5 July 2023 – “Paris Mineral Resource Update” (refer Appendix 1 for Resource Table).
Page | 4
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
The results from the entirety of these drill programs were utilised in the revised Mineral Resource Estimate,
which will now be used to inform mining studies as part of the ongoing Paris Definitive Feasibility Study.
The increase to the Paris silver inventory, is in part due to addition of the recently accessed area at Paris
South, but additionally the inclusion of mineralisation at slightly greater depth which has been refined with
additional drilling in this program. This has also resulted in some areas of the resource estimate being
better defined.
The 2023 updated Mineral Resource Estimate represents an approximate 7% increase in total silver
ounces when compared with the 2021 Mineral Resource Estimate. This increase in ounces is due to the
additional drilling in the south of the deposit, consideration of a 175m depth as having reasonable prospects of economic extraction, and use of a 25g/t silver cut-off which is supported by improved silver price
environment and anticipated project economics. Closer spaced infill drilling in the central zone and further
drilling to the north-east of the deposit has provided a more detailed and deliverable result, with a consequential reduction of resource ounces in these areas.
Table 1 (below) provides a summary breakdown of the 2023 Mineral Resource Estimate which has resulted in an approximate 27% increase in resource tonnes, a 17% decrease in grade for a resultant 7%
increase in contained silver metal to 57Mozs of silver with an approximate 1.5% increase to 99kt of contained lead. The figures in Table 1 are rounded to reflect the precision of the estimates and include rounding errors.
Indicated
Inferred
Total
Paris Mineral Resource Estimates at 25g/t cut-off
Tonnes
Ag
Pb
(million)
g/t
%
17
75
0.50
7.2
67
0.20
24
73
0.41
Ag
moz
41
16
Pb
kt
85
14
57
99
Table 1: 2023 Paris Silver Project Mineral Resource estimate (25g/t silver cut-off grade). As reported to ASX 5 July 2023.
Figure 4 (below) shows the 2023 block model, with the classification criteria distinguished by colour (blue
= Inferred, red = Indicated). Only blocks containing estimates at 25g/t cut off silver shown.
The changes to classification, dimension and distribution of the estimates can be seen with the extension
of both Inferred and Indicated resources into the Paris South area.
Page | 5
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Figure 4: Collar plan showing location of the 76 new holes (yellow dots) over the 2023 resource classification block model,
Indicated (red) and Inferred (blue). As released to ASX 5 July 2023.
Paris Silver Project – Definitive Feasibility Study
With the completion of the resource extension drilling discussed above, and the subsequent updated Mineral Resource Estimate, packages of work to complete the DFS are underway. These include:
Drilling for hydrological testing and groundwater modelling within and surrounding the Paris deposit
footprint. Drilling was completed in June and modelling is anticipated to be completed in July.
On the completion of the Paris hydrology test work, drilling, pump drawdown and recharge testing
of the Hector paleochannel will inform modelling to confirm suitability as a supply of process water.
Data from the Paris pit hydrology testwork will enable final geotechnical assessment of the planned
open pit to be undertaken, including the potential extension of the resource to the south on completion of pit optimisation studies, developed using the updated Mineral Resource Estimate for
Paris.
Metallurgical testwork is focussed on lead recovery and final process plant design, with selection
of samples for dispatch to consulting metallurgical laboratory undertaken in the quarter. Additional
variability analysis of mineralisation and gangue was completed and will be used to inform targeted
testwork to enhance metallurgical knowledge within the deposit.
Engagement with the SA Department for Energy and Mining (DEM), designed to facilitate final
project approvals leading to Mining Lease establishment.
Page | 6
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Tender proposals to close out environmental studies covering the project area in addition to engineering studies.
Advancement of Native Title approvals, continuing the well-established relationship with GRAC,
the Traditional Owners of the land on which Paris sits, with a view to finalising a mining NTMA
enabling development of, and production from, the Paris Silver Project.
Apollo 2023 Exploration Drill Program
A Reverse Circulation (RC) drill program of 2,166m across 12 drill holes was completed in February 2023
with the final results reported in the June Quarter. Drilling aimed to test the projected extension of mineralised epithermal veins intersected in 2022 RC and Diamond Drill programs. Veining was successfully
intersected in Hole PPRC892, which appears visually identical to the veining previously intersected in
Holes PPRC826 and PPDH182 and supported by similar petrological descriptions. These petrological descriptions, whilst similar, describe samples with two slightly varied fluid metal budgets being Fe/Ag/Pb and
Fe/Ca/Zn/Pb/Ag. This suggests that the veins are formed possibly at different times by fracturing and
infiltration by mineralising fluids of different composition but in the same epithermal system.
Figure 5: Plan showing the 2023 drill holes at the Apollo prospect. Smaller grey dots represent historic collars (all previously
reported).
Northwest-oriented gravity low features extending from north of Paris through the Argos and Ares prospects (see Figure 5 above for location) probably reflect paleo-drainage along pre-existing structures and
lithologies prone to rapid weathering (i.e. dolomite), or a faulted graben environment similar to the Paris
deposit. This type of topographic feature, which predates the eruption of the Gawler Range Volcanics
(GRV), is interpreted to be filled with volcaniclastics, providing an ideal host for mineralisation, as seen at
Page | 7
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Paris. These gravity low features continue to the northwest of the current drilling at Apollo and are intersected by multiple cross-cutting structures, many of which are sub-parallel to the dykes associated with
the Paris deposit and with the recently identified Apollo structure. This area is also adjacent to the Uno
Fault, which is a major, regional-scale, structural zone controlling hydrothermal fluid alteration and volcanic
intrusion/eruption along the southern margin of the GRV.
Commentary
Further exploration is planned to identify an epithermal vein system in the area to the immediate northwest
of the current drilling at Apollo where there may also be volcaniclastic fill. These gravity low features to the
north are masked by later volcanic flows in the vicinity of the Uno Fault Zone, providing seals for hydrothermal fluids and resulting in subdued surface geochemical signatures.
Whilst the results from the recent Apollo drilling have not replicated the significant results of prior programs
- such as 8m @ 1,262g/t silver from 149m, including 3m @ 3,167g/t silver from 150m5 - these results
continue to build on the high-grade silver intersections previously drilled at Apollo and provide new target
areas. Mineralisation, petrological observations and geological interpretation, in conjunction with previous
silver intersections, support the contention that the Apollo prospect is in the right geological setting to host
epithermal-type intermediate sulphidation silver-lead-zinc mineralisation.
Other Investigator Tenements
Stuart Shelf Tenements
As at the end of June 2023, Gold Road Ltd (ASX:GOR) had spent approximately $2.4M. Having satisfied
the Stage 2 Commitment of $2M, GRO have notified Investigator of their intention to form the 51:49 Joint
Venture interest in the tenements. Joint Venture documentation is being drafted.
Fowler Domain Tenements
As at the end of June 2023, Osmond Resources Ltd (ASX:OSM) had spent approximately $200k toward
their Stage 1 commitment of $275k.
OSM have informed the Company that they are finalising arrangements to undertake a regional gravity
geophysical exploration across the tenements.
Investigator holds 1.1M OSM shares, which at 31 June 2023 had an approximate value of $209k. These
shares have now been released from escrow.
Curnamona Tenements
A detailed drone aeromagnetic survey covering a number of key prospect areas was commenced in December 2022. Owing to unfavourable flying conditions and the Christmas period a portion of the survey
was postponed by the survey operator. The survey was completed during the June 2023 quarter and is
undergoing processing and analysis work prior.
Earn-In to Molyhil Tungsten-Molybdenum Project
Investigator have entered into a staged Earn-In Agreement with Thor Energy PLC (Thor, ASX & AIM: THR)
to acquire up to 80% of their permitted Molyhil Tungsten Project in Northern Territory6.
5 - ASX 25 August 2022 - Paris Regional Exploration Drilling Results
6 - ASX 24 November 2022: Strategic Earn-In on Molyhil Tungsten Project
Page | 8
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
During the quarter, further field work was undertaken to finalise planning for the 2023 H2 field program
that, subject to gaining necessary approvals, will include confirmatory drilling of the resource, a regional
gravity survey and exploration RC drilling.
A revised Mining Management Plans (MMP) to allow drilling activity, in addition to other regulatory documentation has been submitted during the period. Native Title liaison towards work program approval was
also commenced.
With a previously reported Mineral Resource Estimate7 of 4.38Mt @ 0.27% WO3 and 0.10% Mo for 11.8kt
WO3 and 4.4kt Mo (JORC 2012) and positive Definitive Feasibility Study8 results, the Molyhil Project has
been granted Major Project Status9 by the NT Government which will facilitate the project’s regulatory
approvals. During the June Quarter the Company announced (ASX 30 June) that it had been successful
in an application to the Northern Territory Government for co-funding of an extensive gravity survey over
the Molyhil Tungsten-Molybdenum Project.
Molyhil Gravity Program
Other than a broad (2km x 2km) spacing regional gravity program completed in 2006, no detailed gravity
surveys have been undertaken across the Molyhil Project or the surrounding area. The proposed survey,
conducted on spacings varying from 200m x 100m, down to 20m x 40m in some areas, will provide high
resolution gravity data over the Molyhil deposit and its surrounding area, as shown in Figure 6 (below).
Figure 6: Plan showing the planned gravity program with 20m x40m spaced stations (blue area) over the Molyhil deposit, 60m x
120m spaced stations (red dots) and the broader regional 100m x 200m spaced stations (black dots). Note: the survey does not
impinge on the Native Title exclusion zone shown immediately northwest of Molyhil.
7 – As reported by THR to the ASX 8 Apr 2021
8 – As reported by THR to the ASX 23 Aug 2018
9 – As reported by THR to the ASX 6 July 2020
Page | 9
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
The gravity program will be undertaken in the latter part of the year upon gaining Native Title work clearances and will facilitate regional stratigraphic and structural interpretations, supporting target identification
over a broad area surrounding the Molyhil deposit. Used in conjunction with magnetic interpretation, this
will enable identification and ranking of targets for future drill testing.
CORPORATE
Cash
The Company held $4.5 million cash in Company bank accounts at 30 June 2023.
JMEI Credits
During the quarter, Investigator was advised by the Australian Taxation Office that application for
tax credits under the Federal Government’s Junior Minerals Exploration Incentive (JMEI) scheme
has been assessed and fully allocated.
Under the JMEI scheme:
Investigator has received an allocation of $312,500 in JMEI credits.
Some or all of these JMEI credits may be distributed to eligible Investigator
shareholders as a tax offset or franking credit against the Company’s tax losses for
allowable greenfields exploration expenditure in the 2023/24 financial year.
To be eligible, a shareholder must participate in any fundraising that Investigator undertakes during
the 2023/24 financial year.
Only new shares issued through any fundraising by Investigator will be subject to the JMEI scheme.
Corporate Disclosure and Reporting
In the attached Appendix 5B, the figure of $191,000 (as disclosed in section 6.1) relates to all fees, salaries
and superannuation paid to Investigator’s Directors for the June 2023 Quarter.
TENEMENTS
No new tenements were applied for during the quarter.
Following strategic review, tenement EL6187 (Algebuckina) was not renewed.
Investigator’s tenement holdings at the end of the quarter are detailed in the table below.
Page | 10
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Page | 11
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
UPCOMING NEWS AND RESULTS
In the September Quarter, Investigator anticipates releasing the following information to the ASX:
Financial accounts, Audit and Annual Report for financial year 2022/23.
Commencement of drilling activities at the Molyhil Tungsten Project.
Results from the early-stage exploration work within the Curnamona tenement package.
Results from the hydrological testwork and modelling at the Hector paleochannel – the identified
potential source of process water for operation of the Paris Silver Project.
Further metallurgical outcomes from Paris recovery enhancement and optimisation studies.
For and on behalf of the board.
Andrew McIlwain
Managing Director
For more information:
Andrew McIlwain
Peter Taylor
Managing Director
Media & Investor Relations
Investigator Resources
NWR Communications
+ 61 (0) 8 7325 2222
+ 61 (0) 412 036 231
amcilwain@investres.com.au
peter@nwrcommunications.com.au
About Investigator Resources
Investigator Resources Limited (ASX: IVR) is a metals explorer with a focus on the opportunities for silver-lead, copper-gold and
other metal discoveries. Investors are encouraged to stay up to date with Investigator’s news and announcements by registering
their interest here: https://investres.com.au/enews-updates/
Capital Structure (as at 30 June 2023)
Directors & Management
Shares on issue
1,437,170,017
Dr Richard Hillis
Non-Exec. Chair
Listed Options
232,108,085
Mr Andrew McIlwain
Managing Director
Unlisted Options
28,500,000
Mr Andrew Shearer
Non-Exec. Director
Top 20 shareholders
32%
Ms Anita Addorisio
CFO & Company Secretary
Total number of shareholders
5,501
Page | 12
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Competent Person Statement
The information in this release relating to exploration results is based on information compiled by Mr. Jason Murray who is a fulltime employee of the company. Mr. Murray is a member of the Australian Institute of Geoscientists. Mr. Murray has sufficient
experience of relevance to the styles of mineralisation and the types of deposits under consideration, and to the activities undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the Joint Ore Reserves Committee (JORC) Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Murray consents to the inclusion in this
report of the matters based on information in the form and context in which it appears.
The information in this release that relates to Mineral Resources Estimates at the Paris Silver Project is extracted from the release
titled “Paris Mineral Resource Estimate Update” dated 5 July 2023 and is available to view on the Company’s website www.investres.com.au. The Company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcement and that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The company confirms that the
form and context in which the Competent Person’s findings are presented have not been materially modified from the original
market announcement.
The information in this release that relates to Pre-Feasibility Study undertaken on the Paris Silver Project is extracted from the
release titled “Paris PFS Delivers Outstanding Results” dated 30 November 2021 and is available to view on the Company’s
website www.investres.com.au. The Company confirms that it is not aware of any new information or data that materially affects
the information included in the original market announcement and that all material assumptions and technical parameters underpinning the results in the relevant market announcement continue to apply and have not materially changed.
No new information is presented in this release relating to the Molyhil Project.
All references to Molyhil Mineral Resource Estimates, Ore Reserves, prior Definitive Feasibility Studies have been extracted
from relevant ASX releases by Thor Mining PLC and have not been modified. Competent Persons for all ASX releases below
are referenced in the relevant releases:
ASX 15 January 2018 THR: Clarification of Upgraded Ore Reserve and Extended Minelife, Molyhil Tungsten Project.
ASX 23 August 2018 THR: Upgraded Feasibility Study - Molyhil
ASX 8 April 2021 THR: Molyhil Project, Mineral Resource Estimate Updated
Page | 13
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Appendix 1 – Paris Mineral Resource Estimate10
Table 1: 2023 Paris Silver Project Mineral Resource estimate (25g/t silver cut-off grade).
(Note: Total values may differ due to minor rounding errors in the estimation process)
NOTE:
The information in this release that relates to Mineral Resources Estimates at the Paris Silver Project is extracted from the release titled “Paris Mineral
Resource Estimate Update” dated 5 July 2023 and is available to view on the Company’s website www.investres.com.au. The Company confirms that it
is not aware of any new information or data that materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified
from the original market announcement.
10 – As released to the ASX on 5 July 2023
Page | 14
ASX Release – Investigator
Quarterly Activities Report
30 June 2023
Appendix 2 – Molyhil Mineral Resource Estimate11
Category
‘000
Tonnes
WO3
Grade %
Tonnes
Mo
Grade %
Tonnes
Cu
Grade %
Tonnes
Fe Grade
%
Measured
464
0.28
1,300
0.13
600
0.06
280
19.12
Indicated
2,932
0.27
7,920
0.09
2,630
0.05
1,470
18.48
Inferred
990
0.26
2,580
0.12
1,170
0.03
300
14.93
Total
4,386
0.27
11,800
0.1
4,400
0.05
2,190
17.75
Table 2: Molyhil Mineral Resource Estimate JORC (2012) classification as reported by Thor Energy to the ASX on 8 April 2021. Reported at a cut-off grade of 0.07% WO3 Tungsten.
(Note: Total values may differ due to minor rounding errors in the estimation process, Mineral Resource reported to a 200mRL level which was used to define material that could be
potentially extracted using open pit mining methods).
NOTE: The information in this release that relates to Mineral Resources Estimates at the Molyhil Tungsten/Molybdenum Project is extracted from Thor Energy's ASX release titled “Mineral
Resource Estimate Update, Molyhil Project” dated 8 April 2021 and is available to view on Thor Energy’s website www.thorenergyplc.com. The Company understands that the Molyhil Mineral
Resource Estimate was compiled in accordance with the guidelines of the Australasian Code for Reporting of Identified Mineral Resources and Ore Reserves (JORC, 2012) and that the data
for the Molyhil Mineral Resource Estimate was prepared and validated by Thor Energy under the supervision of Nicole Galloway Warland, a Member of the Australian Institute of Geoscientists.
Thor Energy considered that Ms Galloway Warland had sufficient relevant experience to be considered a “Competent Person” as defined by the JORC Code (2012).
The resource estimate for WO3 and Mo was undertaken by Johan van Zyl, Senior Geostatistician with Golder Associates, a Member of the Australasian Institute of Mining and Metallurgy. Mr
van Zyl was considered by Thor Energy to have sufficient relevant experience to be considered a “Competent Person” as defined by the JORC Code (2012). The resource estimate for Fe and
Cu was undertaken by Stephen Godfrey, Principal Resource Geologist with Resource Evaluation Services, a Fellow of the Australasian Institute of Mining and Metallurgy and a Member the
Australian Institute of Geoscientists. Mr Godfrey was considered by Thor Energy to have sufficient relevant experience to be considered a “Competent Person” as defined the JORC Code
(2012).
The Company confirms that it is not aware of any new information or data that materially affects the information included in Thor Energy's original market announcement, and that the form and
context in which the Competent Person’s findings are presented have not been modified from Thor Energy's original market announcement.
11 – As released to the ASX by Thor Energy on 8 April 2021
Page | 15
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
INVESTIGATOR RESOURCES LIMITED
ABN
Quarter ended (“current quarter”)
90 115 338 979
30 June 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date (12
months)
$A’000
-
-
(a) exploration & evaluation
-
-
(b) development
-
-
(c) production
-
-
(d) staff costs
(164)
(746)
(e) administration and corporate costs
(228)
(768)
-
-
45
96
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
15
1.9
Net cash from / (used in) operating
activities
(347)
(1,403)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(b) tenements
-
-
(c) property, plant and equipment
-
(86)
(644)
(4,502)
(e) investments
-
-
(f)
-
-
(a) entities
(d) exploration & evaluation
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Proceeds from the disposal of:
Current quarter
$A’000
Year to date (12
months)
$A’000
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
(49)
(49)
2.6
Net cash from / (used in) investing
activities
(693)
(4,637)
-
4,527
(a) entities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
-
(212)
3.5
Proceeds from borrowings
-
Share your feedback