Paris DFS Confirms Maiden Ore Reserve, Strong Economics
Released
Released
Announcement PDF
Investigator Silver Limited | ABN: 90 115 338 979 | 47 King St, Norwood SA 5067 Australia
Cautionary Statement
The Definitive Feasibility Study (DFS) discussed herein has been undertaken to assess the technical and economic feasibility of developing
an open pit mine to economically and sustainably exploit the Paris Silver deposit, located in South Australia.
The Paris Silver Project (Paris or Project) is 100% owned by Investigator Silver Limited (Investigator, or the Company).
The Production Target and financial forecasts presented in the DFS are shown on a 100% Project basis. The Ore Reserves and Mineral
Resources underpinning the Production Target have been prepared by Competent Persons in accordance with the JORC Code (2012). The
Production Target underpinning the financial forecasts included in the DFS comprises 86% Indicated Mineral Resources and 14% Inferred
Mineral Resources, and is not based on any Exploration Target or qualifying foreign estimate. During the project payback period of 11 months
(post completion of pre-production works), less than 1% of the Production Target is derived from Inferred Mineral Resources. There is a low
level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in
the determination of Indicated Mineral Resources or that the Production Target itself will be realised.
The economic outcomes associated with the DFS are based on certain assumptions made for commodity prices, exchange rates and other
economic variables, which are not within the Company's control and are subject to change from time to time. Changes in such assumptions
may have a material impact on the economic outcomes.
To achieve the range of outcomes indicatedin the DFS, additional funding will likely be required. Investors should note that there is no certainty
that the Company will be able to raise that amount of funding when needed. It is also possible that such funding may only be available on
terms that may be dilutive to, or otherwise affect the value of the Company’s existing shares. It is also possible that the Company could pursue
other “value realisation” strategies such as a sale, partial sale or joint venture of the Project. If it does, this could materially reduce the
Company’s proportionate ownership of the Project. See also ‘Funding assumption’ in Section 13 and ‘Funding and market conditions’ in
Section 16 for the Company’s funding assumptions and associated risks.
This release contains forward-looking statements. Generally, the words “expect”, “potential”, “intend”, “estimate”, “will” and similar
expressions identify forward-looking statements. By their very nature forward-looking statements are subject to known and unknown risks
and uncertainties that may cause actual results, performance or achievements, to differ materially from those expressed or implied in the
forward-looking statements, which are not guarantees of future performance. Forward-looking statements are necessarily based on
estimates and assumptions that, while considered reasonable by the Company, are inherently subject to significant technical, business,
economic, competitive, political and social uncertainties and contingencies. Since forward-looking statements address future events and
conditions, by their very nature, they involve inherent risks and uncertainties. Actual results in each case could differ materially from those
currently anticipated in such statements. Investors are cautioned not to place undue reliance on forward-looking statements, which speak
only as of the date they are made.
The Company has concluded that it has a reasonable basis for providing the forward-looking statements included in this announcement and
believes it has a reasonable basis to expect that it will be able to fund the development of the Project. However, several factors could cause
actual results or future expectations to differ materially from the results expressed or implied in the forward-looking statements. Given the
uncertainties involved, investors should not make any investment decisions based solely on the results of the DFS or this release. Investors
should consider seeking appropriate professional legal, financial and taxation advice in reviewing this release and all other information with
respect to the Company and evaluating the business, financial performance and operations of the Company. Neither the provision of this
release nor any information contained in this release or subsequently communicated to any person in connection with this release is, or
should be taken as, constituting the giving of investment or financial advice to any person. This release does not take into account the
individual investment objective, financial or tax situation or particular needs of any person.
Competent Persons Statements
Exploration Results: The information in this report relating to Exploration Results is based on, and fairly represents, information and
supporting documentation prepared by Mr Jason Murray who is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM) and
a full-time employee of the Company. Mr Murray has sufficient experience relevant to the style of mineralisation and type of deposit under
consideration, and to the activity being undertaken, to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Murray consents to the inclusion in this report of the matters
based on his information in the form and context in which it appears.
Mineral Resource Estimates: The information in this report that relates to Mineral Resource Estimates at the Paris Silver Project is extracted
from the release titled “Paris Mineral Resource Estimate Update” dated 5 July 2023 and is available to view on the Company’s website. The
Company confirms that it is not aware of any new information or data that materially affects the information included in the original market
announcement, and that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent
Person’s findings are presented have not been materially modified from the original market announcement.
Ore Reserves: The information in this report that relates to Ore Reserves is based on, and fairly represents, information and supporting
documentation prepared by Mr Atish Kumar, who is a member of the Australasian Institute of Mining and Metallurgy (AusIMM) and a consultant
to the Company and is employed by Perth Mining Consultants. Mr Kumar has sufficient experience relevant to the style of mineralisation and
type of deposit under consideration, and to the activity being undertaken, to qualify as a Competent Person as defined in the 2012 Edition of
the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Kumar consents to the inclusion in this
report of the matters based on his information in the form and context in which it appears.
Metallurgy: The information in this report that relates to metallurgical results is based on, and fairly represents, information and supporting
documentation prepared by Mr Matthew Leske who is a member of the Australasian Institute of Mining and Metallurgy (AusIMM) and a
consultant to the Company and is employed by Ammjohn Solutions. Mr Leske has sufficient experience relevant to the style of mineralisation
and type of deposit under consideration, and to the activity being undertaken, to qualify as a Competent Person as defined in the 2012 Edition
of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Leske consents to the inclusion in
this report of the matters based on his information in the form and context in which it appears.
Page | 2
27 February 2026
Paris Silver DFS Confirms High-Margin, Finance-Ready
Development Pathway; Maiden Ore Reserve Declared
Strong economics
across pricing cases1
Pre-tax NPV8 A$1,154m, IRR 93%, payback 11 months from first
production (Spot case US$80/oz, A$115.94/oz).
Consensus case (US$60.18/oz, A$87.22)2
: Pre-tax NPV8 A$618m,
IRR 61%, payback 13 months from first production.
High operating
margin supports
fundability
Strong cash flow generation with a net operating cash flow
margin of 64% under the spot case and 52% at consensus.
AISC: A$39.70/oz (US$27.39/oz).
Low funding
requirement
relative to value
Development funding requirement (max negative cash) of A$260m
(incl. indirects, contingency and working capital). NPV8 to
development funding multiple: 4.4x (Spot) and 2.4x (Consensus).
Conventional, low-
risk development
pathway
Shallow open pit, contract mining, whole-ore cyanide leach +
Merrill–Crowe doré, and wet tailings – a well-proven, low-cost
flowsheet and mine development approach.
11 Year mine life,
staged mining gives
early cash flow
Higher-intensity mining in first 2 years brings forward higher grade
/ lower strip ore and builds stockpiles for later reclaim.
Stockpiles provide
downside
protection and
lender comfort
By the end of the first year of processing, forecast low-grade
stockpiles contain ~1.3 Moz of recoverable payable silver,
equivalent to ~A$120m net realisable value after remaining
processing and selling costs. Net realisable stockpile value peaks
at A$493m in month 56 of processing, providing material project
resilience.
Leverage to silver
price
Holding the mine plan, costs and forex constant, each additional
US$1/oz in the silver price implies A$27m increase in NPV8 and
A$42m increase in life-of-project pre-tax net cash flows.
South Australia –
supportive Tier 1
jurisdiction
Stable regulatory framework, established mining region and
infrastructure base. Permitting program being progressed in close
consultation with government and stakeholders.
District-scale
growth potential
Paris sits within a 15 km mineralised corridor with multiple near-
plant drill targets. Proximity to the planned Paris plant and TSF
(designed with expansion capacity) creates a lower capital,
permitting and environmental hurdle for potential satellite feed
and corridor growth.
1
Note: Outcomes are pre-tax, ungeared (no financing) on a 100% project basis. Unless otherwise stated, evaluation uses AUD:USD 0.69, 8%
discount rate, no escalation. Only the silver price varies between pricing cases –there is no change in mine design or cut-off grade.
2
Consensus Economics January 2026 – median forecast 2031-2035
Page | 3
Commenting on the DFS results and the exciting future of the Paris Silver Project, Managing
Director Lachlan Wallace said:
“The Feasibility Study confirms Paris as a tier-one, high-margin, finance-ready silver
development project with strong leverage to the silver price and a practical near-term
pathway to silver production. The project is a conventional low-risk development – shallow
open-pit, contract mining, and whole-ore leach to produce silver doré; prioritising
operability, schedule certainty and a reliable ramp-up.
Importantly, the Study outcomes are underpinned by a staged mine plan designed to bring
forward higher-grade, lower strip ore, build stockpiles and strengthen resilience through
the funding and ramp-up period. The development funding estimate includes appropriate
allowances and contingency to support a robust, fully-costed funding plan.
Following delivery of this Study, Investigator’s focus now shifts to development, as we
move to advance the DFS cost and schedule through detailed engineering and contracting
to firm up execution certainty, progress permitting, and prepare for financing. This includes
a high-density pre-FID drilling program targeting the first three years of mining to
strengthen grade confidence in the early cash-flow window and support a faster lender
process to deliver more competitive financing outcomes, which includes pricing, covenants
and overall terms.
Our objective is clear – move rapidly and methodically from study into development,
tighten execution certainty, position Paris to be construction-ready and then look to hit the
go-button on building our world-class asset into Australia’s leading, pure silver mine.”
Paris is located close to large mining centres; Whyalla and Port Augusta
Page | 4
1 Executive Summary
Investigator Silver (ASX:IVR) (Investigator or the Company) has completed a Definitive
Feasibility Study (DFS) for the Paris Silver Project, which is located on Central Eyre Peninsula,
~70km north of Kimba and ~7 hours by road from Adelaide.
Paris is designed as a conventional, low technical risk silver development: a shallow open-pit
orebody mined by contract mining, processed through a standard whole-ore cyanide leach
flowsheet with Merrill–Crowe doré recovery, and supported by a wet tailings storage facility.
The execution philosophy prioritises simplicity, constructability and ramp-up reliability, whilst
tailoring design to efficient closure and rehabilitation outcomes.
The Study demonstrates a combination of high operating margin, rapid payback and modest
development funding requirement, supporting a fundable project profile. In addition, early
low-grade stockpiles build a growing on-site metal inventory that provides operating flexibility
and material downside protection for lenders, reducing funding risk in the early years. The
project sits within one pastoral lease with strong ongoing relationships with the landholder in
place with strong recognition of the mutual benefit development offers.
Paris is located in South Australia, a mature and supportive mining jurisdiction with
established infrastructure and a strong regulatory framework. Investigator has maintained
active engagement with government to scope an efficient approvals pathway and has
established constructive relationships with Traditional Owners, with the project design
incorporating cultural heritage considerations and avoidance of sensitive areas.
1.1 Financial outcomes (pre-tax, ungeared)
The DFS presents outcomes on a pre-tax, ungeared basis (no financing) at Spot and Consensus
in Table 1.1. Headline outcomes highlight a high-margin development case with strong
leverage to silver price3
:
• Free-cash generation A$1,866m over ~11 year mine life.
• Pre-tax NPV8 A$1,154m, IRR 93%, and payback 11 months from first production.
• Exceptional operating margin: Net operating cash flow margin of ~64% (Spot) and
~52% (Consensus).
• Silver price leverage: Holding mine plan, costs and forex constant, each additional
+US$1/oz in the silver price increases the NPV8 by ~A$27m and life-of-project pre-tax
net cash flows by ~A$42m.
• Breakeven silver price including capital repayment: ~US$37.35/oz.
• The project exhibits a low development funding requirement relative to value, with
NPV8 to development funding multiples of approximately ~4.4x (Spot) and ~2.4x
(Consensus). Combined with rapid payback and high operating margins, this supports
a financeable profile and a fast transition from construction into free cash generation.
3
Spot case (US$80/oz). At Consensus price (US$60.18/oz): Free-cash generation is $1,038m, Pre-tax NPV8 ~A$618m and IRR ~61%.
Page | 5
Table 1.1 Financial outcomes (pre-tax, ungeared)
Item Unit Definitive Feasibility Study 2026
Economic Assumptions Consensus Spot
Silver Price (USD) US$/oz 60.18 80.00
Silver Price (AUD) A$/oz 87.22 115.94
Exchange Rate AUD: USD 0.69 0.69
Project Economics
Pre-Tax NPV8 A$M 618 1,154
Pre-Tax IRR % 61% 93%
Pre-Tax Payback Period (from first Production) Months 13 11
Pre-Tax Payback Period (from first Capital) Months 36 34
Net operating cash flow margin4
% 52% 64%
All-In-Sustaining-Cost A$/oz 39.70 39.70
Table 1.2 Cash Flow (pre-tax)
Item Unit Definitive Feasibility Study 2026
Cash flow Consensus Spot
Gross Revenue A$M 2,645 3,516
Royalties A$M 118 157
Doré Transport & refining A$M 25 29
Net Revenue A$M 2,502 3,330
On Site Operating Costs1 A$M 1,204 1,204
Net Operating Cash Flow A$M 1,298 2,126
Development Funding (max negative cash)5
A$M 260 260
- Mining Pre-production A$M 39 39
- Process plant A$M 70 70
- Infrastructure A$M 98 98
- Indirect Costs A$M 30 30
- Contingency A$M 23 23
Net Project Cash Flow (Pre-Tax) A$M 1,038 1,866
Figure 1.1 Cash Flow (Pre-Tax)
4
Net operating cash flow margin defined as Net Operating Cash Flow divided by Net Revenue
5
Development funding requirement (maximum negative cash position; including working capital)
(300)
100
500
900
1,300
1,700
2,100
2,500
(200)
(100)
-
100
200
300
400
500
Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11
Cumulative
Cash
Flow
(A$M)
Annual
Cash
Flow
(A$M)
Annual Cash Flow Cumulative Cash Flow
Page | 6
Figure 1.2 Sensitivity – NPV8: Tornado Chart (A$M variance with +/- 20% input change)
Figure 1.3 Sensitivity – NPV8
1.2 Project snapshot
Paris is a proposed 1.5 Mtpa conventional open-pit silver operation producing silver doré,
supported by contract mining and a whole-ore leach processing route. The DFS schedule spans
approximately 11 years including construction and is designed around a staged mining
approach – initially higher-intensity mining to access early ore, followed by steady-state
mining and a later processing period supported by stockpile reclaim.
Table 1.3 LOM Project physicals
Item Unit Definitive Feasibility Study 2026
Life of Mine (LOM) Months Construction + 108 operating
Ore mined and processed Kt 13,395
Waste Mined (including 7.6Mt Mineralised Waste) Kt 79,841
Strip Ratio Waste: Ore 5.96:1
Silver Grade g/t 91
Silver Recovery % 78%
Silver in Doré produced Moz 30
48
103
155
433
433
433
48
92
155
433
433
433
Capex
Discount
Opex
Metallurgical Recovery
Silver Grade
Silver Price
600
800
1,000
1,200
1,400
1,600
-20% -15% -10% -5% 0% 5% 10% 15% 20%
NPV
(A$M)
Silver Price
Operating Cost
Capital Cost
A$1,154m
Page | 7
Figure 1.4 Simple flexible site layout on flat ground
1.3 Mineral Resource Estimate, Ore Reserve Estimate, and mine plan basis
The Paris global Mineral Resource Estimate (JORC 2012)6
contains 57 Moz silver, comprising
Indicated and Inferred Resources. Lead has not been considered in the DFS.
Table 1.4 2023 Paris Mineral Resource Estimate at 25g/t cut-off and to 0mRL
Category Mt Ag g/t Pb % Ag Moz Pb kt
Indicated 17 75 0.5 41 85
Inferred 7.2 67 0.2 16 14
Total 24 73 0.4 57 99
Note: Totals may not sum due to rounding
Table 1.5 2026 Paris Ore Reserve Estimate at varying cut-off grades7
Category Mt Ag g/t Ag Moz
Proven 0 0 0
Probable 12 88 33
Total 12 88 33
Note: Totals may not sum due to rounding
The mine plan includes a component of Inferred Resource material (14% LOM, and less than
1% in the payback period). There is a lower level of geological confidence associated with
Inferred material and no certainty that forecast production targets will be achieved. The DFS
schedule and development strategy prioritise early-stage confidence and minimises Inferred
material exposure in the potential debt-repayment window. Ore Reserves are solely reported
for the Indicated resource category.
6
ASX Announcement 5 July 2023 Paris Mineral Resource Update
7
Cut-off grade varies for each geometalllurgical domain: BT=28.5g/t, BTM=23g/t and DOL=24g/t – refer Section 4.2 for further Ore Reserve
Estimate inputs.
Page | 8
The mine plan is designed to bring forward higher grade and lower strip ratio material early,
supporting strong early cash flow and rapid payback. The first two years utilise a higher-
intensity (dual fleet) mining configuration to accelerate access to early ore and build
stockpiles, before transitioning to steady-state mining and later stockpile reclaim.
Figure 1.5 Pit stages target high grade, low strip ratio early
1.4 Operating strategy, stockpiles and lender de-risking
Operational flexibility and resilience
The DFS incorporates an ore stockpiling strategy that supports consistent plant feed and
provides flexibility in grade management, blending and scheduling. Stockpiles also provide
resilience against short-term disruptions by maintaining a buffer of mined ore available for
processing.
Stockpiles enable grade streaming to maximise NPV and build resilience through early metal
inventory
The staged mining approach builds stocks and enables grade streaming over the life of the
project, with high grade material preferentially presented to the process facility to improve
NPV. This results in head grades averaging 131g/t Ag over the first two years of processing,
compared with the average LOM head grade of 91 g/t Ag.
Page | 9
The stockpiles also act as on-site metal inventory that provides both operational flexibility and
downside protection. By end of the first year of processing, low-grade stockpiles are forecast
to contain approximately ~1.3 Moz of recoverable payable silver, equivalent to ~A$155m of
stockpiled metal value at spot price. On a net realisable basis (after remaining processing costs
and selling charges), this represents approximately ~A$120m of embedded value that can be
realised through processing without additional mining risk. The net realisable value of the
stockpile peaks at A$493m approximately 56 months (~5 years) after operations commence.
This is expected to reduce lender risk and support competitive project finance outcomes.
Figure 1.6 Stockpile Balance (top) and Net Realisable Value of Stockpiles (bottom)
0
1
2
3
4
5
6
Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11
Closing
Stockpile
Balance
(Mt)
High Grade Medium Grade Low Grade
-
100
200
300
400
500
600
700
800
Y0 Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y11
A$M
Processing Cost Net Realisable Value
Construction
Construction
Operations
Operations
Page | 10
1.5 Processing route and performance
The DFS process plant is designed for 1.5 Mtpa throughput and is based on a conventional
crush–grind–leach flow sheet producing silver doré. The design philosophy prioritises proven,
fit-for-purpose equipment and a straightforward layout to support operability, maintenance
access and reliable ramp-up.
Key features include:
• Three-stage crushing into a coarse ore stockpile and reclaim system
• Single 5.75 MW ball mill targeting P80 ~53 µm
• Leach / Merrill–Crowe recovery circuit delivering doré production
• Leading EPMC contractor, Mincore, provided detailed design and cost basis to support
DFS-level engineering, including detailed equipment lists and vendor based price
inputs.
Conventional, well-trodden pathway (low technical risk)
The selected flowsheet and infrastructure approach are standard for comparable operations:
open pit mining, crush and grind, whole-ore cyanide leach, Merrill–Crowe doré production
and wet tailings storage are established methods with extensive operating precedents. The
DFS does not rely on novel processing technology or unproven execution concepts.
Figure 1.7 Conventional process: crush–grind–leach–Merrill–Crowe silver recovery
1.6 Development funding requirement and capital composition
The project’s capital requirement is presented as the development funding requirement,
which is defined as the maximum cumulative negative cash position from first capital
expenditure through ramp-up to positive cash-flow. Development funding includes direct
Page | 11
capital, indirects/owner’s costs, contingency and working capital movements through ramp-
up, and is presented as maximum negative cash. This reflects the practical funding envelope
for construction and ramp-up.
On this basis, the development funding requirement is estimated at ~A$260m, inclusive of
indirect costs, contingency and working capital allowances, without escalation.
Table 1.6 Development funding requirement
Cost Area
Project Capital ($M)
A$M US$M
Mining pre-production (mobilisation + pre-strip prior to first ore processed) 39 27
Processing plant 70 48
Infrastructure (including site services, power, water, TSF, and camp) 98 67
Indirect costs (project execution / delivery costs) 30 21
Contingency 23 16
Development funding requirement (max negative cash) 260 180
Note: 1. Totals may not sum due to rounding. 2. Forex: AUD:USD 0.69
Figure 1.8 Pareto Chart – Capital Costs
Capital is concentrated in a small number of packages, with the largest drivers comprising the
processing circuits (leach/grind/recovery) and remote-site infrastructure required for reliable
operation (notably power, TSF and camps). Contingency is a deliberate DFS-level allowance
reflecting residual uncertainty and execution variability within defined scope.
Mining:
Pre-strip
Contingency
Power
Leaching
TSF
Construction
Grinding
Metal
Recovery
Camp
Construction
camp
Project
Management
Crushing
Site
Services
Construction
Support
Mining
Workshop
Water
Management
CCD
Mining
:
Mob
&
Demob
Road
Reagents
Owners
Costs
Raw
Water
Dam
Site
Construction
Management
Mining:
Diesel
Mining:
Clear
&
Grub
Mining:
Owners
Capital
Plant
Freight
&
Logistics
Detox
Owners
Capital
Communication
Grade
Control
Equipment
Capital
Cost
(A$M)
0
5
10
15
20
25
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Page | 12
1.7 Operating costs and AISC
Operating costs are estimated at DFS level and structured across the three core cost centres:
• Mining: contractor-operated, based on a schedule of rates aligned to the DFS mining
phases and material movement profile.
• Processing: plant labour, reagents/consumables, maintenance, power/fuel, borefield
and Tailings Storage Facility (TSF) operations.
• Site G&A / marketing: site support functions plus transport/refining/royalties.
A large portion of operating cost scales with tonnes processed, so A$/t metrics remain
comparatively stable through the mine life, while A$/oz varies with head grade, particularly in
later years.
Table 1.7 Life-of-mine operating cost summary by phase
Parameter / Cost Component
Capital Phase 1 Phase 2 Phase 3 Total
Dual Fleet Dual Fleet Single Fleet Rehandle
Project Period
Before
processing
Years 3-4 Years 5-8 Years 9-End ~11 years
Mining configuration Two fleets Two fleets Single fleet SP reclaim
Ore stockpile reclaim (kt) - 475 2,141 3,645 6,261
Total material moved (kt) 4,378 35,877 52,981 - 93,236
Waste mined (kt) 4,298 31,985 43,559 - 79,841
Ore mined (kt) 80 3,893 9,422 - 13,395
Strip ratio (waste:ore) 53.5 8.2 4.6 - 5.96
Ore processed (kt) - 2,625 7,125 3,645 13,395
Head grade (g/t Ag) - 131 95 52 91
Silver produced (koz) - 8,140 17,386 4,803 30,329
COSTS (A$M)
Mining capitalised 196 404 31 631
Processing capitalised 95 264 135 494
G&A capitalised 15 42 22 79
Total capitalised 307 709 198 1,204
AISC (A$/oz)
Mining - 24.1 23.2 6.5 20.8
Processing - 11.7 15.2 28.1 16.3
G&A - 1.9 2.4 4.6 2.6
Total - 37.7 40.8 39.1 39.7
UNIT COSTS
Mining (A$/t mined or rehandle) - 5.4 7.3 8.6 6.3
Processing (A$/t processed) - 36.2 37.1 37.0 36.9
G&A (A$/t processed) - 5.9 5.9 6.0 5.9
Total (A$/t processed) - 117 100 52 90
1.8 Key risk mitigation
The DFS identifies the key project risk areas and embeds mitigations in study design and the
forward work program:
• Resource confidence / Inferred material: staged schedule and development strategy
designed to minimise Inferred resource exposure in the potential debt repayment
Page | 13
window; targeted drilling programs planned to improve confidence in early mining
areas. The Production Target underpinning the financial forecast comprises 86%
Indicated Resources, and 14% Inferred Resources. During the project payback period
of 11 months (post the completion of pre-production works), the Production Target
comprises of more than 99% Indicated Resources, and less than 1% Inferred
Resources. The majority of Inferred material is mined and processed towards the end
of the current mine life (refer to Table 5.3 for detailed annual mining and processing
quantum by Resource category).
• Capital execution and cost certainty: DFS-level estimate includes explicit contingency;
next phase focuses on market testing, early contractor engagement and conversion to
a controls-ready baseline.
• Permitting and approvals: Active engagement with South Australian regulators and
structured approvals planning; early scoping to align studies to regulator
requirements.
• Stakeholder and heritage: Strong working relationship with Traditional Owners and
broader community; design and planning incorporate known culturally sensitive areas
and heritage considerations in addition to respecting existing land users.
1.9 Next steps: approvals, execution planning and funding readiness
Following completion of the DFS, the next phase is focused on execution readiness and
funding readiness, including:
• Build-ready definition (study → construction-ready): Front-End Engineering Design
(FEED) to Issued for Construction (IFC) work packs, constructability input, schedule
sequencing, and controls-ready cost and schedule baseline.
• Debt readiness: strengthen grade confidence in early mining areas, prepare lender
data room and response packs to accelerate due diligence and independent technical
review.
• Procurement and contracting strategy: packaging/tendering strategy, early
contractor engagement and market testing, and long-lead procurement planning
(financing-gated).
• Approvals pathway: progress permitting and associated environmental and heritage
programs in collaboration with regulators and stakeholders.
Figure 1.9 outlines a high-level timeline to first silver production. It is noted that this is a best
estimate and subject to change. The timeline assumes long lead items are committed prior
to FID which is subject to funding availability.
Page | 14
Figure 1.9 Timeline to first silver
1.10 District scale growth and expansion potential
Paris is located within the ~15 km Paris Silver Corridor, a district-scale mineralised trend with
multiple drilling targets along strike and in close proximity to the planned processing hub.
Investigator continues exploration drilling within the corridor to expand the initial Paris
footprint and assess the potential for additional near-plant silver deposits.
A key value driver for Paris is that it is bei